During the scheduled time a power maintenance is required at the Zurich data center. During the maintenance the server rack will be retrofitted with ATS in order to have redundancy and further resiliency.
While the maintenance window is 3 hours, our servers are expected to be unavailable for a total of 10-15 minutes. The maintenance is required in order to avoid a 12 hour power outage while the data center replace the main switchgear system on the primary feed.